Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for the fixed percentage of time saved?
Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for the fixed percentage of time saved?
The critical activity has
The critical activity has
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)
String diagram is used when
String diagram is used when
Gantt chart gives information about
Gantt chart gives information about
The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store
The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store
Which of the following conditions are necessary for applying linear programming?
Which of the following conditions are necessary for applying linear programming?
Queueing theory is used for
Queueing theory is used for
The main object of scientific layout is
The main object of scientific layout is
The critical path of a network represents
The critical path of a network represents
Activity slack or float of any event on a PERT/CPM chart is represented by
Activity slack or float of any event on a PERT/CPM chart is represented by
If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good
If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good
The performance of a specific task in CPM is known as
The performance of a specific task in CPM is known as
Break-even analysis consists of
Break-even analysis consists of
Merit Rating is the method of determining worth of
Merit Rating is the method of determining worth of
Critical Path Net Work helps an engineer
Critical Path Net Work helps an engineer
Which of the following statement is correct?
Which of the following statement is correct?
Work sampling is applied for
Work sampling is applied for
Tick the odd man out
Tick the odd man out
Travel charts provide
Travel charts provide
When slack of an activity is positive
When slack of an activity is positive
Work sampling observations are taken on the basis of
Work sampling observations are taken on the basis of
The two bin system is concerned with
The two bin system is concerned with
Dummy activities are used to
Dummy activities are used to
A systematic job improvement sequence will consist of
A systematic job improvement sequence will consist of
The assumption in PERT is
The assumption in PERT is
Critical path moves along the activities having total float of
Critical path moves along the activities having total float of
When slack of an activity is negative
When slack of an activity is negative
Travel charts are used to
Travel charts are used to
Acceptance sampling is widely used in
Acceptance sampling is widely used in
Simplex method is the method used for
Simplex method is the method used for
Gantt charts provide information about
Gantt charts provide information about
The value engineering technique in which experts of the same rank assemble for product development is called
The value engineering technique in which experts of the same rank assemble for product development is called
The product layout
The product layout
The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of
The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of
In order that linear programming techniques provide valid results
In order that linear programming techniques provide valid results
Replacement studies are made on the following basis
Replacement studies are made on the following basis
Work study is concerned with
Work study is concerned with
In a line organization
In a line organization
In the perpetual inventory control, the material is checked when it reaches its
In the perpetual inventory control, the material is checked when it reaches its
The most important function of inventory control is
The most important function of inventory control is
The time which results in the least possible direct cost of an activity is known as
The time which results in the least possible direct cost of an activity is known as
The main disadvantage of line organisation is
The main disadvantage of line organisation is
String diagram is used
String diagram is used
Acceptance sampling is used in
Acceptance sampling is used in
The main advantage of line organisation is its
The main advantage of line organisation is its
In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his efficiency reaches
In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his efficiency reaches
Line organization is suitable for
Line organization is suitable for
In the cost structure of a product, the selling price is determined by the factors such as
In the cost structure of a product, the selling price is determined by the factors such as
What does symbol 'V' employ in work study
What does symbol 'V' employ in work study
Scheduling gives information about
Scheduling gives information about
A big advantage of PERT over Gantt charts is that in the former case
A big advantage of PERT over Gantt charts is that in the former case
Which of the following equations is not in conformity with others?
Which of the following equations is not in conformity with others?
The first method invented for planning projects was
The first method invented for planning projects was
In product layout
In product layout
Basic motion time study gives times for basic motions in ten thousandths of
Basic motion time study gives times for basic motions in ten thousandths of
A critical activity has
A critical activity has
The aim of value engineering is to
The aim of value engineering is to
Merit rating is the method of determining the
Merit rating is the method of determining the
Routing prescribes the
Routing prescribes the
What does symbol 'O' imply in work study?
What does symbol 'O' imply in work study?
In process layout
In process layout
In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:
In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:
A feasible solution to the linear programming problem should
A feasible solution to the linear programming problem should
The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as
The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as
The term 'value' in value engineering refers to
The term 'value' in value engineering refers to
What does symbol 'D' imply in work study?
What does symbol 'D' imply in work study?
Expediting function consists in keeping a watch on
Expediting function consists in keeping a watch on
Which of the following is independent of sales forecast?
Which of the following is independent of sales forecast?
Pick up the correct statement about relationship between various floats
Pick up the correct statement about relationship between various floats
PERT analysis is based on
PERT analysis is based on
In PERT analysis, critical path is obtained by joining events having
In PERT analysis, critical path is obtained by joining events having
Time study is carried out
Time study is carried out
Which of the following statement is correct?
Which of the following statement is correct?
Work study is most useful
Work study is most useful
Job evaluation is the method of determining the
Job evaluation is the method of determining the
CPM has following time estimate
CPM has following time estimate
Standard time is defined as
Standard time is defined as
Work study comprises following main techniques
Work study comprises following main techniques
Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.
Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.
Slack of various events on the critical path in PERT/CPM chart
Slack of various events on the critical path in PERT/CPM chart
In micro-motion study, therblig is described by
In micro-motion study, therblig is described by
Inventory management consists of
Inventory management consists of
In a PERT chart
In a PERT chart
In time study, the rating factor is applied to determine
In time study, the rating factor is applied to determine
PERT has following time estimate
PERT has following time estimate
The salient feature of functional organisation is
The salient feature of functional organisation is
The average time recorded by work study man for an operation is called
The average time recorded by work study man for an operation is called
Which one of the following techniques is used for determining allowances in time study?
Which one of the following techniques is used for determining allowances in time study?
The main objective of work measurement is to
The main objective of work measurement is to
F. W. Taylor introduced a system of organisation known as
F. W. Taylor introduced a system of organisation known as
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
Current assets include
Current assets include
The grouping of activities into organizational units is called
The grouping of activities into organizational units is called
A low unit cost can be obtained by following
A low unit cost can be obtained by following
Material handling in automobile industry is done by
Material handling in automobile industry is done by
Percent idle time for men or machines is found by
Percent idle time for men or machines is found by
One time measurement unit (TMU) in method time measurement system equals
One time measurement unit (TMU) in method time measurement system equals
The routing function in a production system design is concerned with
The routing function in a production system design is concerned with
In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if
In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if
Bin card is used in
Bin card is used in
M.T.M. is used to
M.T.M. is used to
Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
A CPM family includes
A CPM family includes
For a product layout the material handling equipment must
For a product layout the material handling equipment must