A critical activity has
A critical activity has
Percent idle time for men or machines is found by
Percent idle time for men or machines is found by
Queueing theory is used for
Queueing theory is used for
When slack of an activity is negative
When slack of an activity is negative
The performance of a specific task in CPM is known as
The performance of a specific task in CPM is known as
In process layout
In process layout
String diagram is used
String diagram is used
The aim of value engineering is to
The aim of value engineering is to
The assumption in PERT is
The assumption in PERT is
The routing function in a production system design is concerned with
The routing function in a production system design is concerned with
Work sampling observations are taken on the basis of
Work sampling observations are taken on the basis of
The main object of scientific layout is
The main object of scientific layout is
In the perpetual inventory control, the material is checked when it reaches its
In the perpetual inventory control, the material is checked when it reaches its
If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good
If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good
Basic motion time study gives times for basic motions in ten thousandths of
Basic motion time study gives times for basic motions in ten thousandths of
The average time recorded by work study man for an operation is called
The average time recorded by work study man for an operation is called
Job evaluation is the method of determining the
Job evaluation is the method of determining the
Work sampling is applied for
Work sampling is applied for
Merit Rating is the method of determining worth of
Merit Rating is the method of determining worth of
In a line organization
In a line organization
Acceptance sampling is used in
Acceptance sampling is used in
Dummy activities are used to
Dummy activities are used to
Work study comprises following main techniques
Work study comprises following main techniques
When slack of an activity is positive
When slack of an activity is positive
Material handling in automobile industry is done by
Material handling in automobile industry is done by
A low unit cost can be obtained by following
A low unit cost can be obtained by following
Tick the odd man out
Tick the odd man out
The first method invented for planning projects was
The first method invented for planning projects was
Which of the following equations is not in conformity with others?
Which of the following equations is not in conformity with others?
Gantt chart gives information about
Gantt chart gives information about
Simplex method is the method used for
Simplex method is the method used for
Break-even analysis consists of
Break-even analysis consists of
Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for the fixed percentage of time saved?
Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for the fixed percentage of time saved?
The time which results in the least possible direct cost of an activity is known as
The time which results in the least possible direct cost of an activity is known as
Travel charts provide
Travel charts provide
Critical Path Net Work helps an engineer
Critical Path Net Work helps an engineer
The main advantage of line organisation is its
The main advantage of line organisation is its
The main disadvantage of line organisation is
The main disadvantage of line organisation is
Standard time is defined as
Standard time is defined as
Which one of the following techniques is used for determining allowances in time study?
Which one of the following techniques is used for determining allowances in time study?
Replacement studies are made on the following basis
Replacement studies are made on the following basis
In a PERT chart
In a PERT chart
The product layout
The product layout
The value engineering technique in which experts of the same rank assemble for product development is called
The value engineering technique in which experts of the same rank assemble for product development is called
String diagram is used when
String diagram is used when
Which of the following conditions are necessary for applying linear programming?
Which of the following conditions are necessary for applying linear programming?
Merit rating is the method of determining the
Merit rating is the method of determining the
Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it
Routing prescribes the
Routing prescribes the
Which of the following statement is correct?
Which of the following statement is correct?
In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his efficiency reaches
In the Emerson efficiency plan, a worker receives only his daily wage and no bonus is paid till his efficiency reaches
The critical path of a network represents
The critical path of a network represents
In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:
In Lincoln plan (one type of group incentive plan), the amount of the profit which an employee receives in addition to the guaranteed basic pay/wages, is based on:
In time study, the rating factor is applied to determine
In time study, the rating factor is applied to determine
Pick up the correct statement about relationship between various floats
Pick up the correct statement about relationship between various floats
In PERT analysis, critical path is obtained by joining events having
In PERT analysis, critical path is obtained by joining events having
Activity slack or float of any event on a PERT/CPM chart is represented by
Activity slack or float of any event on a PERT/CPM chart is represented by
Critical path moves along the activities having total float of
Critical path moves along the activities having total float of
In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if
In queuing theory, the nature of the waiting situation can be studied and analysed mathematically if
A big advantage of PERT over Gantt charts is that in the former case
A big advantage of PERT over Gantt charts is that in the former case
Acceptance sampling is widely used in
Acceptance sampling is widely used in
The salient feature of functional organisation is
The salient feature of functional organisation is
What does symbol 'V' employ in work study
What does symbol 'V' employ in work study
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)
The probabilistic time is given by (where to = Optimistic time, tp = Pessimistic time, and tn = Most likely time)
The term 'value' in value engineering refers to
The term 'value' in value engineering refers to
Line organization is suitable for
Line organization is suitable for
A CPM family includes
A CPM family includes
CPM has following time estimate
CPM has following time estimate
In product layout
In product layout
Work study is concerned with
Work study is concerned with
Work study is most useful
Work study is most useful
Which of the following statement is correct?
Which of the following statement is correct?
Inventory management consists of
Inventory management consists of
What does symbol 'D' imply in work study?
What does symbol 'D' imply in work study?
Travel charts are used to
Travel charts are used to
The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store
The wastage of material in the store is taken into account by the following method in the evaluation of the material issued from the store
Which of the following is independent of sales forecast?
Which of the following is independent of sales forecast?
A feasible solution to the linear programming problem should
A feasible solution to the linear programming problem should
Gantt charts provide information about
Gantt charts provide information about
The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as
The artificial activity, which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as
For a product layout the material handling equipment must
For a product layout the material handling equipment must
PERT has following time estimate
PERT has following time estimate
The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of
The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of
Slack of various events on the critical path in PERT/CPM chart
Slack of various events on the critical path in PERT/CPM chart
Bin card is used in
Bin card is used in
In order that linear programming techniques provide valid results
In order that linear programming techniques provide valid results
One time measurement unit (TMU) in method time measurement system equals
One time measurement unit (TMU) in method time measurement system equals
In micro-motion study, therblig is described by
In micro-motion study, therblig is described by
Time study is carried out
Time study is carried out
PERT analysis is based on
PERT analysis is based on
The most important function of inventory control is
The most important function of inventory control is
M.T.M. is used to
M.T.M. is used to
In the cost structure of a product, the selling price is determined by the factors such as
In the cost structure of a product, the selling price is determined by the factors such as
What does symbol 'O' imply in work study?
What does symbol 'O' imply in work study?
Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.
Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time.
Current assets include
Current assets include
The critical activity has
The critical activity has
Scheduling gives information about
Scheduling gives information about
F. W. Taylor introduced a system of organisation known as
F. W. Taylor introduced a system of organisation known as
Expediting function consists in keeping a watch on
Expediting function consists in keeping a watch on
The grouping of activities into organizational units is called
The grouping of activities into organizational units is called
The main objective of work measurement is to
The main objective of work measurement is to
A systematic job improvement sequence will consist of
A systematic job improvement sequence will consist of
The two bin system is concerned with
The two bin system is concerned with
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to
If TL is the largest allowable event occurrence time, total activity slack (s) is equal to